Visit 7 - Not Long To Go Now!

Rain was in the air as I entered the site this afternoon. Work continues to progress well, the completion of the park is on schedule and expected to be open at the end of April with the official opening jam to be held no Sunday 11th May


The reclaimed banked corner originally outside of the park fence is now filled with earth and was being skilfully sculpted with a mini digger.
 Pretty much all the coping and metal section has been welded in place around the park area and most of the ground work has been completed on the banks, 1/4 pipe and corners. These should be poured this week.


.


Both flat bars have been welded. The finishing of the joins will be completed soon as will the ends of the handrail down the steps. These have now been poured too.




The up down ledge and pyramid/driveway surrounding it are near complete with only one side of the pyramid needing to be poured. 




I'll be visiting the site again on Wednesday along with an architect to perform a quality inspection so I'll be posting another update very soon.